Remodelling Works at the Sheraton Hotel Santiago

We would like to inform you of the remodelling projects at the Sheraton Hotel Santiago, which just began and will probably take one year. All 379 rooms of the hotel will be completely remodelled and modernised. In order to keep the hotel running, the works will be done in two stages: the first 200 rooms will be remodelled between April 2015 and September 2015, and the remaining 179 rooms between October 2015 and March 2016. Daily working hours are scheduled from 09:00 am to 06:00 pm, so guests will not be disturbed by noises in the mornings and evenings. The hotel can be booked for groups during the 2015/16 season, but due to the reduced number of available rooms, early booking may be necessary. The San Cristobal tower is not affected by the remodel.